What should be included in a welding robot factory acceptance test? At a minimum, the test should establish that the delivered cell matches the agreed configuration, produces acceptable welds on representative parts, meets the required production cycle, and responds correctly to safety and control commands. The results should be recorded against acceptance criteria agreed before the test.
A successful demonstration of robot movement or a few attractive weld beads is not enough to establish production readiness. The most useful factory acceptance test (FAT) follows the intended operating sequence: load representative parts, run the programmed welds, inspect the results, and check how the cell handles faults and recovery. Its scope should reflect the contract, the welding process, and the equipment available at the supplier’s facility.
The supplier and buyer should agree on a written test plan before anyone arrives at the factory. It should identify the equipment and software to be tested, the parts and consumables to be used, the inspection methods, and the evidence needed for acceptance. A checklist without measurable pass criteria can leave both sides with different interpretations of a successful result.
For each major requirement, the plan should state what will be measured, how it will be measured, and what result is acceptable. For example, “adequate weld quality” is difficult to verify. A more useful requirement identifies the welds to inspect, the applicable drawing or welding specification, the inspection method, and the acceptance limits.
The plan should also identify who supplies the test material. If the buyer provides parts, they should represent the expected material grade, thickness, joint design, fit-up and surface condition. If the supplier makes substitute parts, both sides should agree on their limitations. A clean, accurately prepared sample may prove the programmed path while revealing little about how the cell handles the normal variation in incoming work.
Decide in advance how many parts will be welded and inspected, whether the sequence will run continuously, and whether more than one part variant must be demonstrated. The sample size should be sufficient to assess the agreed requirement; one successful cycle gives limited evidence of repeatability.
Begin with a physical and document check against the equipment list and approved layout. This establishes what is actually being accepted before performance testing begins.
Check access as well as presence. Can an operator load the part without an awkward reach? Can the torch, contact tip and liner be serviced? Is there a practical route for removing the finished assembly? These observations may expose layout problems that a component list cannot. If a fixture or peripheral has been replaced during manufacture, record the change and assess its effect on the agreed performance.
Run the cell through its intended sequence, starting with part loading and ending with removal of the welded part. The sequence may include fixture clamping, positioner movement, seam finding, welding, torch cleaning and transfer to the next station. Verify each function that forms part of the supplied scope.
First, use an appropriate controlled method to check clearances and programmed motion. Then run the complete cycle under the agreed test conditions. Watch for collisions or near misses, cable interference, unstable torch orientation, excessive repositioning, and welds that are difficult to reach. A path that works with an empty fixture may behave differently once clamps, cables and a production-sized part are in place.
Where the cell handles multiple part types, demonstrate the agreed changeover: selecting the correct program, adjusting or changing tooling, and confirming that the fixture locates the next part correctly. If manual intervention is required, record it. The buyer needs to understand which steps are automatic and which depend on an operator.
Test the intended response to representative faults, such as a missing part signal, a clamp that has not confirmed its position, loss of arc or a wire-feed fault, where these functions are included. The operator should be able to identify the fault from the control interface and follow the agreed recovery procedure. Recovery deserves its own demonstration: restarting after an interruption can create incomplete welds or collisions if the robot resumes from an unsuitable position.
Weld quality should be assessed against the drawings, welding procedure and inspection requirements agreed for the job. The test should cover the relevant joint types and positions, including welds that are difficult for the torch to access. Inspecting only the easiest seam can leave important performance questions unanswered.
Visual inspection can check features such as weld location, continuity, bead appearance and visible defects against the specified criteria. Depending on the application, the agreed plan may also require dimensional checks, destructive examination or nondestructive testing. State which welds will be examined, who will perform the inspection, and whether results must be available before acceptance. A visually consistent bead alone does not establish internal soundness or penetration.
Record the welding parameters and consumables used during the accepted run, including those needed to reproduce the result. The record should also identify the part, program and fixture configuration. If a supplier changes parameters between attempts, retain the sequence of changes and identify the settings used for the final accepted samples.
Fit-up variation is often a practical boundary on robotic welding performance. If the contract requires the system to accommodate a specified gap, misalignment or part-position range, include representative samples at those limits. If no such range has been agreed, the FAT result should be understood in relation to the tested fit-up; it should not be treated as proof that the cell will handle every variation arriving from upstream production.
Cycle time needs a defined start and end point. For example, the measurement might run from the start of an automatic cycle to the signal that the welded part is ready for unloading. If the required figure includes loading, unloading, indexing or operator actions, those steps must be included in the measurement and performed as planned for production.
Measure the agreed number of consecutive cycles using acceptable parts and the final welding program. Record individual times as well as the method used to calculate any average. A fast dry run, a single cycle with reduced weld length, or a run that excludes necessary handling time will not answer the same question as a production cycle.
Repeatability should be considered alongside speed. A cell that meets its target once but needs frequent manual adjustment may struggle to sustain output. Observe whether parts locate consistently, clamps operate reliably, the robot starts each weld in the intended position, and the process completes without unexplained stops. The duration and number of cycles should be agreed in advance and proportionate to the confidence required.
The FAT should include functional checks of the safety measures supplied with the cell, following the agreed test procedure and the applicable project requirements. Depending on the design, these may include emergency stops, guard-door interlocks, protective devices, reset functions and operating modes. Verify the expected stop response and the conditions for a safe restart; record any function that cannot be tested at the supplier’s site.
Review how the operator accesses the cell for loading, setup, cleaning and fault recovery. The safety concept must account for the actual tasks, including maintenance access and the movement of positioners or other machinery. A safety device can operate correctly in isolation while the overall workflow still presents an access problem.
Check interfaces with equipment outside the cell where practical. This can include start and stop signals, part-present signals, fault reporting, and communication with an upstream or downstream machine. If the connected equipment is unavailable, agree on a simulation method and record what the simulation proves. Final integration and site safety validation remain necessary when the complete installation and its operating environment are available.
The FAT record should provide a traceable account of what was tested and what happened. It should identify the equipment and software configuration, test parts, programs, inspection results, measured cycle times, safety checks and any deviations from the test plan. Photographs or inspection records can support the results where useful.
The handover package should include the documents specified in the contract, such as operating and maintenance instructions, electrical and pneumatic drawings, parts lists, backup copies of robot and controller programs, welding settings, and instructions for fault recovery. Confirm the format and transfer method for software backups, and identify any passwords or access arrangements needed by the buyer’s authorized personnel.
Not every open item has the same effect on acceptance. A missing label may be correctable before shipment; a failure to meet the required weld quality or cycle time may require retesting. For each exception, record the issue, its effect, the responsible party, the corrective action and the deadline. State whether acceptance is withheld, conditional on completion, or granted for the tested scope.
Some conditions cannot be reproduced at the factory, including the buyer’s utilities, production flow and final connections. Put those items into a site acceptance plan with their own criteria and responsibilities. That gives both parties a clear boundary between what the FAT has demonstrated and what still needs to be proven after installation.