What should a Chinese 9-axis welding robot factory test before shipment?

What should a Chinese 9-axis welding robot factory test before shipment?

Nov 06, 2026

Before shipment, a Chinese 9-axis welding robot factory should demonstrate more than a successful weld. The relevant evidence is that the configured axes move within agreed limits, coordinated motion maintains the required torch position, representative welds meet specified acceptance criteria, and protective functions respond correctly to foreseeable faults.

The factory acceptance test (FAT) should use the actual control configuration, safety devices, welding equipment and fixtures included in the order. A test performed on a different robot or without the external axes may show that individual components work, but it does not establish that the delivered system works as an integrated cell.

Define what “nine axes” means before testing

A nine-axis system does not have one universal mechanical layout. It may consist of a six-axis robot plus a travel rail and a two-axis positioner, or another combination of robot and external motion. The acceptance documents should identify each axis, its drive and controller, range of travel, payload or workpiece limit, and whether it operates in coordinated or independent mode.

This distinction matters because the principal risk is often at the interface. A robot can position its torch accurately while stationary, yet produce a poor weld when a positioner rotates because the external-axis coordinate system, direction or pivot point is incorrect. The FAT should therefore identify which axes must move together during production and include those combinations in the test program.

Before the factory runs the cell, the acceptance plan should also state the test parts, welding process, inspection method, instruments, tolerances and required records. Where the purchase specification does not define a tolerance, a demonstration alone cannot establish acceptance: the parties need to agree on a measurable criterion before interpreting the result.

Check axis calibration, travel and coordinated motion

Begin with the mechanical configuration: verify mounting, fasteners, cable routing, lubrication points, mechanical stops and the condition of rails, gearboxes and positioner bearings. Check that each axis moves in the indicated direction and reaches its intended working range without abnormal noise, binding or interference. Limits and homing or reference procedures should match the controller configuration.

Position checks should cover more than a single convenient point. Use suitable calibrated measuring equipment to examine representative positions across the intended working envelope, including the ends of a rail or the relevant angular range of a positioner. Repeat approaches to selected points and record the method, direction of approach and results. Repeatability and absolute positioning accuracy are different properties: returning consistently to the wrong location does not prove that a programmed path is accurate.

For coordinated motion, run the actual or representative path with the rail and positioner active. Check torch position and orientation relative to the workpiece throughout the path, particularly at changes in direction, near travel limits and where several axes accelerate together. Verify the tool center point, robot base frame, workpiece frame and positioner pivot calibration. A dry run at reduced speed helps identify interference, but a further run at the agreed operating speed is needed to assess dynamic behavior.

Acceptance should be based on the specified path or weld requirements, not on the combined number of axes. If a project has a demanding path tolerance, agree on how it will be measured under load, including the fixture and workpiece mass. A controller display alone is not an independent measurement of the torch-to-workpiece relationship.

Use representative welds to validate the complete process

Trial welds should reflect the intended production conditions: material grade and thickness, joint preparation, gap, position, consumables, shielding gas and fixture arrangement. Record the welding procedure or agreed parameter set, including current, voltage, travel speed, wire feed where applicable, gas flow and any weaving or tracking settings. The test should cover the joints and positions specified in the acceptance plan, rather than selecting only the easiest seam.

Inspect welds against the agreed drawing, welding procedure and applicable product or fabrication standard. Visual inspection can reveal problems such as inconsistent bead profile, visible porosity, undercut or missed joint location, but it cannot establish internal soundness or penetration by itself. Where required, use the specified nondestructive examination or destructive tests, such as macrosections or bend tests. Acceptance limits and the number and locations of samples must be agreed in advance.

Run enough consecutive cycles to expose issues that a single weld can conceal, such as wire feeding instability, torch contamination, fixture movement or overheating. The required run length depends on the intended duty and contract; it should be long enough to exercise the relevant sequence, not treated as a universal endurance certification. Record interruptions, parameter changes and corrective actions rather than reporting only the final successful run.

Where the cell uses seam tracking, touch sensing or through-arc correction, introduce controlled joint variations within the agreed operating range. Verify both correction performance and the system’s response when the joint is outside that range. A tracking system should not silently compensate for an incorrectly calibrated fixture without that condition being identified.

Clamping deserves separate attention because movement or distortion at the joint can be mistaken for a robot accuracy problem. For comparison, a dedicated Longitudinal seam welding machine may use pneumatic fingers and a backing mandrel to hold a straight seam. That arrangement is not evidence of nine-axis capability, but it illustrates why a robotic cell’s fixture, backing and clamping sequence must be included in weld acceptance rather than assessed as unrelated accessories.

Test protective functions as a complete safety system

Safety checks should be derived from the cell’s documented risk assessment and safety-function design. Verify the physical safeguarding supplied with the system, including guards, interlocked access points, protective devices and the separation of personnel from robot and external-axis movement. The test boundary should be clear if fencing or other safeguards will be installed only at the destination.

Functionally test every emergency-stop device and access interlock included in the shipment. Confirm that actuation produces the intended stop of hazardous motion and other relevant hazards, that the condition is indicated, and that releasing or resetting the device does not itself cause an unexpected restart. Test the restart sequence, including any required reset from a location with an adequate view of the hazardous area.

For each operating mode, verify the intended safeguards: automatic operation, manual or teach operation, and any maintenance or setup mode provided. Where enabling devices and reduced-speed functions are part of the design, confirm that they operate as specified, including their effect on external axes. A robot stopping while a positioner or rail continues to create a hazard is not an acceptable system-level result unless the safety design specifically accounts for that behavior.

Test foreseeable faults and recovery conditions defined in the safety validation plan. These can include loss of electrical power, interruption and restoration of air supply, a guard opened during operation, communication faults between controllers, and a protective device being actuated during external-axis movement. Determine whether hazardous motion stops as designed and whether stored energy, gravity or a clamped workpiece introduces additional risks. Do not simulate electrical or safety-circuit faults without an authorized procedure and appropriate controls.

Record the safety function tested, operating conditions, expected response, actual response and any corrective action. A successful emergency-stop demonstration does not by itself validate the entire safety control system; validation also depends on the design, implementation and verification of the relevant safety functions.

Inspect electrical, welding and utility interfaces

Confirm the delivered supply voltage, frequency, phase, protective conductor arrangement and utility requirements against the order and destination installation conditions. Inspect the control cabinet for identification, terminal security, cable protection, segregation and signs of damage. Electrical checks should follow the applicable standard and a documented procedure, using competent personnel and suitable instruments.

IEC 60204-1 addresses electrical equipment of machines and provides a framework for relevant electrical verification. Depending on the equipment and applicable requirements, tests can include protective bonding continuity and other electrical checks. The test procedure must account for sensitive electronics and manufacturer instructions; applying an inappropriate test voltage can damage equipment without providing meaningful assurance.

Operate the welding source, wire feeder, torch cooling where fitted, gas controls and extraction interfaces included in the contract. Check gas and coolant connections for leakage under the specified conditions, and verify that cables and hoses remain clear throughout the full range of motion. Observe whether cable dress packs twist, stretch or rub when the robot and positioner move together. An acceptable static installation can still fail after repeated articulated movement.

Fault indications should be understandable and recoverable. Test the agreed responses to conditions such as wire-feed failure, loss of arc or inadequate coolant flow when the system is equipped to detect them. Clarify which faults stop welding only and which must also stop motion according to the process and safety design.

Relate standards to the actual delivery and destination

The applicable requirements depend on the destination, delivery date, system boundary and contractual specification. ISO 10218-1 and ISO 10218-2 address industrial robot safety and robot applications or cells respectively; ISO 12100 provides a general machinery risk-assessment framework. ISO 13849-1 may be relevant to the design of safety-related parts of control systems. The applicable editions and any regional adoptions should be identified in the project documentation rather than assumed from a generic list.

For equipment placed on the EU market, determine the applicable machinery legislation and other relevant acts, together with the conformity assessment obligations for the complete assembly. CE marking is not a substitute for an acceptance test, and a component certificate does not automatically establish conformity of the integrated cell. The responsible party should provide the applicable declaration, instructions and supporting safety information for the delivered scope.

Agree on the division of responsibility when a cell is shipped without final fencing, extraction, utilities or site integration. Factory testing can validate the supplied configuration, but it cannot confirm site-dependent protective distances, installation quality or final interactions with neighboring machinery. Those items need a defined site acceptance or commissioning check before production use.

Preserve evidence through packing and handover

The shipment record should connect test results to the equipment actually dispatched. Identify the robot, controllers, welding source, external-axis drives and safety devices by model and serial number where available. Include the approved configuration, program and parameter backups, calibration data, drawings, electrical and pneumatic schematics, manuals, spare-parts information and the FAT report.

List deviations openly. A useful record states the requirement, measured or observed result, disposition, responsible party and closure evidence. If a test cannot be completed until site installation, identify the reason, temporary restrictions and the specific site test required; it should not be recorded as a factory pass.

Before packing, return axes to the specified transport positions, fit mechanical restraints where required, protect machined surfaces and connectors, and mark lifting points and handling instructions. Confirm that transport locks and removed components are listed for reassembly. Document the condition of the equipment and crates, then retain the configuration backups separately from the machinery.

The strongest pre-shipment acceptance package links each important claim to a defined test and an identifiable result. It also distinguishes what was proven at the factory from what remains dependent on installation, guarding and commissioning at the final site.